allincx.com / Guides / Integrated systems testing
Guide · Testing

Integrated systems testing (IST) and load banks

The integrated systems test is the moment a data center proves it can lose power, cooling or controls without dropping the IT load. This guide covers the scenarios, the pass criteria, how to size load banks and what the test needs in fuel, power and air.

Updated October 20268 min readBy Ziya DemirData center project directorFounder of allindatacenter.com

In short

  • IST is commissioning Level 5: all systems together, at design load, with failures simulated.
  • Pass criterion: the IT load never drops and temperatures stay inside the design range.
  • Load banks replace the IT: resistive for kW, reactive for power factor, rack-mount heaters for airflow in the white space.
  • Simulating 5 MW for 8 hours uses about 40 MWh, about 10,800 l of diesel on gensets, and rejects 5 MW of heat.
Purpose

What an integrated systems test proves

Lower levels prove that each device and each system works. IST proves that they work together: that the UPS holds the load while the generators start, that the cooling restarts in the right order after a transfer, that controls and fire systems interact as the design intends. It is run with the building's own operators, so it also tests the procedures.

Scenarios

Typical IST scenarios and pass criteria

ScenarioExpected responsePass criterion
Utility failureUPS on battery, gensets start and take loadNo load drop; transfer inside the design window
Genset fails to startRedundant sets share the loadLoad carried; alarm at EPMS
UPS module faultRedundant modules or the other path hold loadNo transfer to unprotected bypass
Utility returnRetransfer to utilityTransition as designed; gensets cool down
Cooling unit failureStandby chiller, CRAH or CDU startsSupply air or water inside design range
Pump or valve failureStandby pump takes overFlow and pressure recover
Controls or network lossPlant fails safe and keeps runningNo unplanned stop; alarms raised
Fire alarm cause and effectDampers, shutdowns, releasesActions match the matrix
Black building startSequenced restartRestart without manual help

The number of scenarios grows with topology: a 2N or distributed-redundant design has more failure paths to prove than an N+1 block. The IST library on the home page lists the same nine.

Equipment

Load bank types

TypeUse
Resistive (500 kW mobile, 1,000 kW container)Full kW load on UPS, generators and switchgear; tests at unity power factor
Reactive (resistive-inductive or capacitive)Leading or lagging power factor for generator synchronisation and voltage regulation
Rack-mount heater banks (~15 kW)Simulate servers in the racks, so airflow, containment and liquid loops see real heat

Large banks at the switchgear test the power train; rack-mount banks in the white space test the cooling. A full IST usually needs both.

Sizing

Sizing the test, not just the plant

QuantityFormula
Load bank unitsIT load to simulate ÷ unit rating, rounded up
Apparent powerkVA = kW ÷ PF
Energy during the testkWh = kW × hours at full load
Diesel if gensets carry itlitres ≈ kWh × 0.27 l/kWh (check the genset datasheet)
Airflow through air-cooled banksm³/h = kW ÷ (1.2 × 1.006 × ΔT) × 3,600
Worked example

Simulating a 5 MW hall for 8 hours

QuantityValue
Units at 1,000 kW (or at 500 kW)5 (or 10)
Apparent power at PF 1.05,000 kVA
Energy = 5,000 kW × 8 h40,000 kWh
Diesel = 40,000 × 0.2710,800 l
Heat to reject5,000 kW ≈ 1,422 RT
Airflow through banks at ΔT 15 K≈ 994,000 m³/h

Banks outside the building need space, cabling, a fuel plan and somewhere for the hot air to go. Banks inside the white space put their heat into the cooling system, which is the point of the test, so the cooling must be ready first.

Size your own testThe load bank bench gives units, energy, diesel, heat and airflow.
Open the bench →
Practice

Running the IST day

  • Prerequisites: L4 complete, issues log clear of critical items, controls and EPMS trending live.
  • Scripts: every scenario has steps, expected responses, pass criteria and sign-off boxes, agreed before the day.
  • Safety: a stop procedure, a single test director, radios, and clear isolation of live parts.
  • Data: record temperatures, voltages and transfer times continuously; a pass needs evidence, not memory.
  • Re-tests: a failed scenario is fixed and re-run, and anything it touched is re-tested.
Questions

Questions about IST and load banks

How big should the load banks be?

Large enough to load each hall to its design IT load, in units that can be stepped to test partial loads as well.

Why use reactive load banks?

Generators behave differently at leading or lagging power factor. Reactive banks check synchronisation and voltage regulation that resistive banks cannot show.

How long does an IST take?

Usually one to several days per hall, depending on the number of scenarios and re-tests. The planner estimates it with the other levels.

Is load bank testing repeated after handover?

Yes. Annual load bank tests on generators and UPS are recommended as part of maintenance.

Sources

Sources

  • ASHRAE Guideline 0; common data center IST practice.
  • Diesel 0.27 l/kWh is a typical full-load rate; air 1.2 kg/m³, cp 1.006 kJ/kg·K.
  • Worked figures are screening values, not a test plan.
Next

Keep reading